Electrification of feeders of 132 KV section of the 400/230/132 KV Nakhlestan substation , Bafq city
|
|
With the completion of installation, testing and commissioning of the second and third phases of development of Nakhlestan Bafq transmission substation, the 132 kV feeders 702, 703, 710 and 711 was successfully connected to the existing part of the substation under supervision of GNEC experts on 21 February 2023 .
|
|